Royd Moor Wind Farm
Royd Moor Wind Farm |
|
Location of Royd Moor Wind Farm
|
Country |
England |
Location |
6 km west of Penistone, South Yorkshire |
Coordinates |
|
Commission date |
1993 |
Owner(s) |
E.ON |
|
Power station information |
Primary fuel |
Wind |
Generation units |
13 Bonus 500 turbines |
|
Power generation information |
Installed capacity |
6.5 MW |
The Royd Moor Wind Farm is located at Penistone, South Yorkshire, England, and consists of thirteen 500 kW turbines. The site is located approximately 6 km north west of Penistone, above the A628 trunk road between Sheffield and Manchester. The turbines are set in two parallel, staggered rows of six and seven,[1] on a ridge in hilly fell land lying 320 m above sea level.
These turbines were completed in 1993 and are 35m in height to the hub and have a rotor diameter of 37m. The maximum output is 6.5 MW, equivalent to the annual energy required to power 3300 homes.[2]
References
- ^ "E.ON UK - Royd Moor". www.eon-uk.com. http://www.eon-uk.com/about/996.aspx. Retrieved 2009-03-11.
- ^ "The OPET Network - Technical Sheet of THERMIE Project Renewables - Wind Energy (RWE-10)". cordis.europa.eu. http://cordis.europa.eu/opet/fiches/rwe-10.htm. Retrieved 2009-03-11.
External links
|
|
Power stations |
|
|
|
|
Active
|
|
|
Closed
|
|
|
Proposed/Future
|
|
|
|
|
|
|
|
Active
|
|
|
Closed
|
|
|
Proposed/Future
|
|
|
|
|
Active
|
|
|
Closed
|
Foss Island
|
|
Proposed
|
Allerton Park Quarry
|
|
|
|
|
|
|
|
Organisations |
|
|